Select Page

As part of the reconstruction of various streets project, work on Junior Parkway will begin Monday, September 24, 2018. The road will be completely closed between Briarleigh Drive and Bettie Lane beginning Tuesday, September 25.

A detour will be posted using Briarleigh, Boston, West 130th, Colony, Joseph and Bettie. The complete closure is necessary to allow the street’s profile to be adjusted to correct existing drainage issues. The road will be closed until late October, weather permitting.

July 10, 2018

The Laurel Road Reconstruction Phase 1 project is scheduled to begin Monday, July 16. The road will be closed to through traffic between Pearl Road and Maxwell Boulevard. The posted detour is via Pearl Road, Center Road and Maxwell Boulevard. Local traffic will be maintained in the eastbound direction only between Pearl Road and just east of Brintnall Drive. Residents of Laurel Road between Pearl and Brintnall will only be able to access their homes via Pearl Road during construction, along with residents of Stone Manor, Hobbits Glen, and Meadowland Drive. Residents of Clemson, Eastwood, Mary Ellen and Brintnall are asked to avoid Laurel Road during construction.

Residents of Laurel Road between Brintnall and Maxwell will be able to access their homes via Maxwell.

This traffic pattern will be in place until late October. Eastbound local traffic will be maintained at all times, but delays are likely in the work zone.

July 27, 2018

The County has completed its work on Sleepy Hollow, which is now open.

 

July 18, 2018

Medina County Engineers are planning on culvert replacements and ditching on Sleepy Hollow between Josephine and Gaylann next week. Sleepy Hollow will be closed to all traffic at Etta starting Monday morning July 23 and will reopen to traffic by Friday evening July 27. The detour route will be West 130th to SR 3 to Hamilton to SR 42 if traveling westbound and reverse for eastbound.

July 26, 2018

Medina County is still planning on starting the milling and resurfacing of Substation Road Monday, July 30 and they anticipate construction to last for 3 weeks. They plan to start at Hamilton and head north through Brunswick.

There are two intersections in Brunswick that will be affected. They are Wolff Drive and Cottonwood lane. The contractor plans to mill off approximately 2” of asphalt and place 3.25” of new asphalt. In doing that they will feather the asphalt back on the side streets around 20’ to provide a smooth transition.

See the Substation tab for previously released information.

 

July 23, 2018

Medina County Engineers are planning on resurfacing Substation Road through the Brunswick area the week of July 30th. Traffic will be maintained but will be down to one lane in the active construction area. The County will be milling 2.5” of asphalt pavement and placing 2.75” of new asphalt.

Currently the transitions from Substation onto Wolff and Cottonwood are steep. They anticipate transitioning the new asphalt around 20’ onto the side streets to provide a better transition.

August 29, 2018

Beginning Friday morning, August 31, Eastwood Drive will be closed at Laurel Road for intersection paving. The closure will last approximately 10 days. During this period there will be no access to Eastwood Drive from Laurel Road, and vice versa. A detour will be posted along Mapes and Brintnall Drives. Laurel Road eastbound local traffic will not be affected.

As a reminder, Laurel Road is closed to through traffic between Pearl Road and Maxwell Boulevard. Local traffic is maintained in the eastbound direction only between Pearl and Brintnall.

Thank you for your patience as we work to expedite the reconstruction of Laurel Road.

 

August 9, 2018

Pinewood is being resurfaced between Laurel Road and Applewood. Traffic will be maintained but it is recommended that non-local traffic avoid the area until work is completed.

 

August 8, 2018

South Carpenter Road will be closed for one day only on  Wednesday, August 8 for a Brunswick Hills culvert replacement project.

 

July 27, 2018

Brunswick City Schools will be doing asphalt repairs to Boyer Drive August 6 & 7. Boyer will remain open during repairs.

Share This