Road Construction Areas

City Engineer

Slip-lining

Stormwater pipe repair work will occur for roughly 90 days beginning on 8/13/2025. Slip-lines will be installed as needed on Charlotte Dr., Pearl Rd., Twain Cir., Western Reserve Dr., and Lares Ln. Insight has been contracted to complete the work and will notify homes in the work areas by hanging informational flyers on their front doors.

Randall-Sheri-Rose Project

The Randall-Sheri-Rose Project started on June 27. The first step is sawcutting. Resident notices were passed out the morning of June 26. All work is on Randall Drive, Sheri Drive, and Rose Drive.

Catch Basin Repairs

Traffic delays are expected on South Carpenter from Monday 8/11/2025 to 8/21/2025 due to catch basin repairs. Flaggers and police will on site to control traffic during work hours.

2024 Concrete Program

The contracting company that is completing the work on Van Buren Drive mobilized on May 13, 2025. This project is carried over from the 2024 Concrete Repair Program.

2025 Asphalt Program

Specialized Construction, Inc. has been selected to perform the work. Weather dependent, the project will last from April 2025, until late July 2025. The safety of the public and construction workers is of the utmost importance during the construction of the project. Your patience and cooperation through the construction process is greatly appreciated. Should you have any questions in regard to this project, please feel free to contact:

  • Operations Manager, Jeremy Clink
    (216) 407-2895
  • Project Manager, Greg Kascmarik, Sr.,
    (216) 390-8333
  • Specialized Construction Office,
    (216) 271-3363

Thank you in advance for your cooperation.

Households within these construction areas will be notified by mail or door hanger before work begins.

Work areas on existing concrete streets/asphalt overlay.

 

StreetNotesLength
Ruth DriveEntire Street1,750'
Pennys DriveRuth Drive to HN 860420'
Charlotte DriveEntire Street1,240'
Francis BlvdHN 3627 to HN 3663 (near Charlotte)400’
Carlisle DriveEntire street835’
Coventry DriveCarlisle Drive to Laurel Road320’
Berwick DriveCarlisle Drive to Chelsea Drive470’

Work areas on existing asphalt streets.

 

StreetNotesLength
Princeton DriveCenter Road to Oxford Drive1,700’
Oxford DriveEntire street except Western Reserve Drive intersection area3,700’
Diana DriveCenter Road to Oxford Drive1,750’

List of fog seal streets.

 

StreetNotesLength
Waite Farms LaneEntire street1,500’
Hartwick CircleEntire street800’
Wellford WayEntire street1,700’
Frost CircleEntire street430’

Additional streets receiving asphalt surface treatment.

 

StreetNotesLength
Magnolia DriveJudita Drive to HN 38563,050'
Bruce DriveEntire Street2,300'
Mars DriveEntire Street2,000'
Dennis LaneQueens Drive to Gary Boulevard1,900'
Regal DriveEntire Street2,550'

Minor work, and projects managed by other entities will not be included on this page.

Road Construction is permitted:

Monday-Friday
7:00 am-7:00 pm

Weekends are discouraged,
but construction may occur
8:00 am-7:00 pm

Brunswick Road Construction:

The City of Brunswick alternates asphalt construction and concrete construction by ward annually. This strategy ensures that each ward receives attention and reduces overall costs by localizing work zones. Once project parameters are determined, the City will request bids and Council will approve the contractor.

Click the image below to view a map of street improvements that occurred from 2015 to 2023.