Road Construction Areas
City Engineer
Slip-lining
Stormwater pipe repair work will occur for roughly 90 days beginning on 8/13/2025. Slip-lines will be installed as needed on Charlotte Dr., Pearl Rd., Twain Cir., Western Reserve Dr., and Lares Ln. Insight has been contracted to complete the work and will notify homes in the work areas by hanging informational flyers on their front doors.
Randall-Sheri-Rose Project
The Randall-Sheri-Rose Project started on June 27. The first step is sawcutting. Resident notices were passed out the morning of June 26. All work is on Randall Drive, Sheri Drive, and Rose Drive.
Catch Basin Repairs
Traffic delays are expected on South Carpenter from Monday 8/11/2025 to 8/21/2025 due to catch basin repairs. Flaggers and police will on site to control traffic during work hours.
2024 Concrete Program
The contracting company that is completing the work on Van Buren Drive mobilized on May 13, 2025. This project is carried over from the 2024 Concrete Repair Program.
2025 Asphalt Program
Specialized Construction, Inc. has been selected to perform the work. Weather dependent, the project will last from April 2025, until late July 2025. The safety of the public and construction workers is of the utmost importance during the construction of the project. Your patience and cooperation through the construction process is greatly appreciated. Should you have any questions in regard to this project, please feel free to contact:
- Operations Manager, Jeremy Clink
(216) 407-2895 - Project Manager, Greg Kascmarik, Sr.,
(216) 390-8333 - Specialized Construction Office,
(216) 271-3363
Thank you in advance for your cooperation.
Households within these construction areas will be notified by mail or door hanger before work begins.
Work areas on existing concrete streets/asphalt overlay.
| Street | Notes | Length |
|---|---|---|
| Ruth Drive | Entire Street | 1,750' |
| Pennys Drive | Ruth Drive to HN 860 | 420' |
| Charlotte Drive | Entire Street | 1,240' |
| Francis Blvd | HN 3627 to HN 3663 (near Charlotte) | 400’ |
| Carlisle Drive | Entire street | 835’ |
| Coventry Drive | Carlisle Drive to Laurel Road | 320’ |
| Berwick Drive | Carlisle Drive to Chelsea Drive | 470’ |
Work areas on existing asphalt streets.
| Street | Notes | Length |
|---|---|---|
| Princeton Drive | Center Road to Oxford Drive | 1,700’ |
| Oxford Drive | Entire street except Western Reserve Drive intersection area | 3,700’ |
| Diana Drive | Center Road to Oxford Drive | 1,750’ |
List of fog seal streets.
| Street | Notes | Length |
|---|---|---|
| Waite Farms Lane | Entire street | 1,500’ |
| Hartwick Circle | Entire street | 800’ |
| Wellford Way | Entire street | 1,700’ |
| Frost Circle | Entire street | 430’ |
Additional streets receiving asphalt surface treatment.
| Street | Notes | Length |
|---|---|---|
| Magnolia Drive | Judita Drive to HN 3856 | 3,050' |
| Bruce Drive | Entire Street | 2,300' |
| Mars Drive | Entire Street | 2,000' |
| Dennis Lane | Queens Drive to Gary Boulevard | 1,900' |
| Regal Drive | Entire Street | 2,550' |
Minor work, and projects managed by other entities will not be included on this page.
Road Construction is permitted:
Monday-Friday
7:00 am-7:00 pm
Weekends are discouraged,
but construction may occur
8:00 am-7:00 pm
Brunswick Road Construction:
The City of Brunswick alternates asphalt construction and concrete construction by ward annually. This strategy ensures that each ward receives attention and reduces overall costs by localizing work zones. Once project parameters are determined, the City will request bids and Council will approve the contractor.
Click the image below to view a map of street improvements that occurred from 2015 to 2023.